Step
9:
Enter
Estimate
This is the main screen where the breakdown of the bid is created and
the costs are entered.
Create Bid Breakdown:
Enter Sections (S):
The estimate and the resulting bill of quantities can be grouped into
main sections. To create a section, point to “Current Bid”
in the bid breakdown window and click on the “Create New Section
Icon”. Enter the description of the section in the “Notes”
box. You can also setup sub-sections by pointing to the section and
following the same procedure. You can setup an unlimited number of sub-sections.
Enter Items (I):
Point to the appropriate section and click on the “Insert New
Bid Line” icon. Under Detail in the right window enter the Item
Number, Type, Description, Quantity, Unit of Measure and Status.
Select
Item Type:
By default an item is assumed to be a “Direct” cost item,
also referred to as a bid item. Items can also be tagged as “Indirect”, “Alternate”,
"Plant" or "Engineering". “Indirect” items are normally
site overhead items that are automatically spread over direct items
when calculating the final bid prices. “Alternate” items
are setup for comparison only and are not included in the total.
"Plant" consist of fixed plant costs that can be spread across a range
of direct items. "Engineering & Development Cost" are summarized
separately from Construction Costs.
Select Line Status:
By default any line in the bid, including items, are initially assumed
to be “Plug” rates. The unit rate or total plugged cost
can be entered directly here. If resources are entered into the line,
the status automatically switches to “Bid”. If a quote is
awarded, the status changes to “Quote”. To enter a cash
allowance, switch the status to “Allow”.
Enter Activities (A):
Point to the appropriate item and click on the “Insert New Bid
Line” icon. The system will allow the user to add up to 20 more
activity levels below an item. Resources can only be
entered at the lowest level. A quotation can be awarded at any level
and will override all cost below that level. Under detail in the right
window enter the Line Number, Description, Quantity, Unit of Measure
and Status.
Tag Lines
for Alternate Breakdowns:
Point to the appropriate line in the bid, then under detail, enter or
drill down to select previously entered tags. For alternate breakdowns
are available including Bid (Procurement) Packages, Work Groups, Joint
Venture Comparison or Location. Various reports are available that summarize
the bid according to these alternate breakdowns. |